The following documents are a mandatory requirement from each subcontractor.
Section C: Subcontractor’s Billing Procedures & Documents
C1. Billing packages must be delivered monthly, no later than the 25th of the month by electronic format to accounting@mjdixon.ca.
C2. Each billing package should include:
C2. – Progress billing for the period and any supporting documentation
C2. – Statutory Declaration for second and all subsequent progress draws
C2. – Valid WSIB Worker’s Compensation Certificate of Clearance
C2. – Certificate of Insurance naming M.J. Dixon Construction Limited as additional insured for a minimum of $5,000,000